Issue SEQR Determination October 30, 2019
Draft Scoping Document June 3, 2020
Public Review and Comment Early June to Early July 2020
Final Scoping Document February 3, 2021
Draft GEIS and Guidebook Mid March 2021
Public Review and Comment Mid March to Mid April 2021
Hold Public Hearings Early April 2021
Final GEIS Early May 2021
Publish Finding Statements Mid May 2021