EEIP Projected Schedule

EEIP SEQR Milestones
Task Date
Issue SEQR Determination Late October 2019
Draft Scoping Document Late November 2019
Public Review and Comment Late November to Late December 2019
Final Scoping Document Mid January 2020
Draft GEIS and Guidebook Early february 2020
Public Review and Comment Early February to Late March 2020
Hold Public Hearings Mid February to Mid March 2020
Final GEIS Late April/Early May 2020
Publish Finding Statements Mid May 2020

* This is an anticipated schedule that complies with DEC regulatory timeframe requirements, however it is subject to change during the environmental review process. The Canal Corporation will update it as the environmental review process progresses.